The Trump administration enacted sweeping global tariffs in April 2025 under the International Emergency Economic Powers Act. Although subsequent trade agreements have been reached with several traditional allies of the Unites States (including the United Kingdom, Japan and South Korea), the legal uncertainty surrounding the application of the tariffs remains complicated.
The administration’s tariff policies have changed frequently since first being announced, and the unpredictability of their application can be more detrimental than the tariffs themselves. The tariffs especially impact the construction and development industries because increases in the costs of building materials and products only serve to delay projects and make them more expensive. Fortunately, there are contractual mechanisms that can be implemented to protect owners and contractors, helping to curb current levels of uncertainty and, in many cases, allowing projects to move forward.
The impacts of the new tariffs have been significant for materials that are vital to construction projects, including steel, aluminum, lumber, copper, concrete, drywall, appliances and other electronic component parts. While the market initially absorbed some increases in material costs because of pauses in implementation and decreases in energy costs, the tariffs are expected to significantly increase the costs of new projects, which could significantly delay projects and decrease profit for contractors. According to the Producer Price Index (PPI) from the U.S. Bureau of Labor Statistics, various construction commodities reflected year-over-year price increases in August, including aluminum mill shapes (up 22.8%); construction sand, gravel and stone (up 7.3%); copper wire and cable (up 12.2%); plywood and lumber (up 4.8%); and steel mill products (up 13.1%).
As a result of the imposition of tariffs, contractors are increasingly insisting on cost-plus contracts at the negotiating table, and owners are insisting on guaranteed maximum price contracts. Neither of these contract types adequately addresses the increased material costs caused by tariffs; they simply shift those costs to one of the parties through change orders. Change orders are ineffective at addressing significantly increased costs because they require the agreement of both parties and do not provide a mechanism to terminate the project if agreement cannot be reached, resulting in disputes that delay projects and erode the trust between parties.
Likewise, contingency and allowance clauses are not particularly effective because the amounts typically budgeted into such clauses are not sufficient to cover significant cost increases. Substantially raising the amounts of contingencies and allowances is not feasible because lenders require certainty in project costs and are unwilling to issue debt for projects that have high variances.
Relying on force majeure clauses to address increased costs associated with tariffs is also an inadequate solution. Courts have been reluctant to apply force majeure clauses for economic conditions that may make a project less profitable, or unprofitable for one party, because losing money on a project does not prevent performance.
Price adjustment clauses offer the most effective solution in construction contracts to equitably address price increases caused by tariffs. Parties negotiate these clauses, which include a specific process to address significant increases in material costs at the outset of a project. Parties are more likely to reach agreement on the parameters of how to manage increased costs before a project begins, unlike the change order process, where one party will have leverage over the other party. And unlike force majeure clauses, price adjustment clauses are enforced by the courts as long as they rely on objective standards and are allowed by the Federal Acquisition Regulation.
The primary challenge to inserting a price adjustment clause into an existing or a new contract is convincing the opposing party to agree to its terms. Both parties must compromise, and it is important for the party with the most leverage during the negotiations to recognize that their leverage could be diminished by economic factors beyond their control in the future.
The wording of price adjustment clauses is imperative to their effective applicability. The clauses need to include triggers, cost-sharing mechanisms, ceilings, and options for parties if the price increases are not sustainable after application of the price adjustment mechanisms.
Price Adjustment Triggers
Cost-sharing Mechanisms
Ceilings and Options
Other Important Terms
The inclusion of price adjustment clauses in construction contracts should be strongly considered as a solution to control and quantify rising material costs resulting from the current administration’s expansive tariff program. Care should be taken to ensure price adjustment clauses are fair to both parties and contain objective criteria for when they are triggered and how they are applied to ensure they are enforceable.
Richard F. Whiteley and Phillip L. Sampson are partners in the Houston office of the Bracewell law firm, where Whiteley chairs the firm’s construction litigation practice group.